PCMS were approached recently by Wycombe Carpet Centre to solve a problem for them. They had outgrown the carpet storage facility on site, and needed to find a way to store additional materials in safe, secure and stable conditions.

We came up with a straight forward solution. The yard to the rear of the shop unit was carefully assessed, and we proposed demolishing the existing shed and replacing it with a purpose built two-storey unit of permanent construction. The new storage unit will be more flexible, and makes available a sizeable increase in storage capacity. This will allow Wycombe Carpet Centre to hold more stock, and consequently offer a better service to customers.

Once a proposal and drawings had been approved by the client, an approach was made to Wycombe District Council for pre-application planning advice. Following this, an application for full planning permission was submitted, and this was granted in August. Wycombe Carpet Centre should hopefully have the new storage unit under construction before the end of the year.

0 comments:

Post a Comment

Note: only a member of this blog may post a comment.

 
Webmaster: AnnWebCom
Copyright 2009 Porter Consulting and Management Services Limited ~ all rights reserved